Modified contracts caps construction costs, revises completion date for SRS salt waste facility

Modified contract caps future construction costs

Tuesday, June 18, 2013 3:27 PM
Last updated 9:08 PM
  • Follow Latest News

The contractor building an important facility to process Cold War waste from Savannah River Site’s underground storage tanks has agreed to a modified contract that caps future construction costs and revises the completion date to Dec. 31, 2016.

The $1.4 billion Salt Waste Processing Facility, which is 72 percent complete, was supposed to commence operations in 2009, then 2011 and then delayed again until 2015 – a date the U.S. Department of Energy acknowledged in January was “no longer achievable.”

Under the terms of the modification, Parsons Infrastructure & Technology Group Inc. agreed to cap future costs at $540 million – and aim for a projected completion cost of $530 million – and will pursue incentives to reduce costs and meet the new completion date on time.

Incentives include an agreement that the parties will share cost under-runs for the final completion cost, with a maximum incentive for Parsons of $30 million.

Parsons would pay half of any additional cost overruns that exceed $530 million but are less than $550 million. Cost overruns beyond $550 million are solely Parsons’ responsibility.

The agreement includes a schedule incentive in which Parsons could earn up to $2 million a month for earlier completion but would pay DOE $2 million for each month past the 2016 deadline.

Of the 36 million gallons of radioactive Cold War nuclear waste once stored in SRS tanks, 33 million gallons were liquid and salt cake forms suitable to enter the salt waste facility, which will separate high-activity radionuclides from low-activity salt waste.

After separation, the high-activity salt waste will be encapsulated in glass at the Defense Waste Processing Facility and stored nearby until disposal in a geologic repository.

The Salt Waste Processing Facility will replace interim facilities at the site. The existing Saltstone Facility opened in 1990 and was modified last year to improve efficiency and prepare it for new roles after the modern plant is completed.

Comments (1) Add comment
ADVISORY: Users are solely responsible for opinions they post here and for following agreed-upon rules of civility. Posts and comments do not reflect the views of this site. Posts and comments are automatically checked for inappropriate language, but readers might find some comments offensive or inaccurate. If you believe a comment violates our rules, click the "Flag as offensive" link below the comment.
wildman
1119
Points
wildman 06/19/13 - 04:57 am
0
0
DOE

Has a DOE project ever been completed on time and under budget? If so I have never read about it. This is ridiculous, how can you be this late and still be rewarded millions of dollars? Try that in the private sector, you will be out of business. Guess it's easy when it's not your money you play with. Give me a break.