Proposed MOX funding cut, alternatives examined

Wednesday, April 10, 2013 5:12 PM
Last updated 11:25 PM
  • Follow Latest News

The mixed oxide fuel plant being built at Savannah River Site “may be unaffordable,” the Obama administration said Wednesday in fiscal 2014 budget requests that would trim $132.7 million from the project and slow its construction.

The MOX plant, designed to dispose of plutonium from surplus nuclear bombs by blending it into commercial reactor fuel, is three years behind schedule and its projected cost recently grew from $4.9 billion to $7.7 billion.

The administration said it fully supports the National Nuclear Security Administration’s mission to dispose of weapons-grade plutonium but must explore options other than MOX.

“This current plutonium disposition approach may be unaffordable … due to cost growth and fiscal pressure,” the budget summary said, adding that officials will “assess the feasibility of alternative plutonium disposition strategies.”

That assessment, along with reduced funding, will result “in a slowdown of MOX Fuel Fabrication Facility Construction in 2014,” the proposal said.

MOX construction received $452.7 million in fiscal 2012, when the last budget was adopted, and $478.7 million under a 2013 continuing resolution. The fiscal 2014 proposal of $320 million would be a cut of $132.7 million – or 29.3 percent.

Also slashed in the budget plan was Savannah River Site’s Environmental Management budget, which pays for the site’s major cleanup and waste-processing activities and the Savannah River National Laboratory.

SRS received $1,187,782 in 2012 and a similar sum under the 2013 resolution. The 2014 proposal is $99.5 million less, representing an 8.4 percent cut.

In its narrative, however, officials said the requested $1,088,200 will still support the liquid waste program, which includes operating the Defense Waste Processing Facility and the Saltstone Facility and continued closure activities for liquid waste Tanks 5 and 6.

The site and its contractors employ about 11,000 workers, including about 2,300 at the MOX construction site.

Comments (4) Add comment
ADVISORY: Users are solely responsible for opinions they post here and for following agreed-upon rules of civility. Posts and comments do not reflect the views of this site. Posts and comments are automatically checked for inappropriate language, but readers might find some comments offensive or inaccurate. If you believe a comment violates our rules, click the "Flag as offensive" link below the comment.
Little Lamb
48880
Points
Little Lamb 04/10/13 - 07:32 pm
1
1
Schedule

If you slow down the MOX project, you inevitably increase the cost. But since Obama and his budget minions never managed a business, they don't understand that principle.

ColCo
919
Points
ColCo 04/11/13 - 06:42 am
0
1
Voids nuclear proliferation treaty with Russia

I was under the impression that the Russians were building a similar plant and if either party doesn't complete and operate the facility, a significant nuclear proliferation treaty will be voided. On the other hand, if MOX is shut down, SRS could move back into production mode.

Riverman1
93313
Points
Riverman1 04/11/13 - 08:28 am
1
1
Cover it all up and call it

Cover it all up and call it Ellenton.

bubbasauce
24260
Points
bubbasauce 04/11/13 - 09:07 am
0
1
Obama's administration and

Obama's administration and his policies are destroying job creation for this country and guess what? That's his plan!

Back to Top

Search Augusta jobs