Government

More News | | | Editor

Repairs to Thurmond Dam floodgates to end by August, cost more

Wednesday, Feb. 22, 2012 8:46 PM
Last updated Thursday, Feb. 23, 2012 1:27 AM
  • Follow Government

Workers have completed maintenance and repairs to 14 of Thurmond Lake’s 23 spillway gates in a project that could take a few months longer and cost more than anticipated.

Back | Next
Repairs have been completed on 14 of 23 spillway gates at Thurmond Lake. The project might cost more than expected.  SARA CALDWELL/STAFF
SARA CALDWELL/STAFF
Repairs have been completed on 14 of 23 spillway gates at Thurmond Lake. The project might cost more than expected.

Contractors using $3.9 million in American Recovery and Reinvestment Act funding began work in February 2010, when U.S. Highway 221 over the dam was reduced to one lane and a traffic light was installed.

The scope of the project was later expanded to address corrosion and rust on the lifting mechanisms in some of the gates, raising the cost to $5.5 million. It later increased again to $6.2 million. The current contract calls for completion in August.

“The contractor is currently on gate 15 and has to get to gate 23,” said Thurmond project manager Scott Hyatt. “We expect work to be complete well before that, but weather or other unforseen delays could push it back.”

The contractor is Atlantic Marine Corp. of Virginia Beach, Va.

Because of the construction, lake levels were to be kept 2 feet below full pool – at 328 feet above sea level instead of the 330-foot level. However, because of extended drought, the reservoir has remained lower than usual in recent months and was at 321.92 feet Wednesday morning.

The lake normally fills to its full pool of 330 feet by mid-April, but the newest Army Corps of Engineers projections foresee the lake remaining between 322 and 323 feet through early May, unless large amounts of rain fall.

Comments (3) Add comment
ADVISORY: Users are solely responsible for opinions they post here and for following agreed-upon rules of civility. Posts and comments do not reflect the views of this site. Posts and comments are automatically checked for inappropriate language, but readers might find some comments offensive or inaccurate. If you believe a comment violates our rules, click the "Flag as offensive" link below the comment.
writerrick
0
Points
writerrick 02/22/12 - 10:53 pm
1
0
Same ole, same ole.

Same ole, same ole.

RoadkiII
6703
Points
RoadkiII 02/23/12 - 04:52 am
1
0
Why does EVERY gov't project

Why does EVERY gov't project take long and cost more than anticipated? I was a general contractor once. When I signed a contract with a customer I got paid what the contract called for. The only time I got any more was an occasional change order agreed to by both parties. It's time for the gov't to hold contractors to the original price.

southern2
6629
Points
southern2 02/23/12 - 10:38 am
1
0
Article says "The lake

Article says "The lake normally fills to its full pool of 330 feet by mid-April". If this happened wouldn't it be "abnormal"? The last time April saw 330' was 7 years ago in 2005. The lake has only been at full pool (330') for 49 days in the last 6 years. Not much bang for the buck.

Back to Top

Search Augusta jobs