The U.S. Department of Energy’s federal loan guarantee program – of which Plant Vogtle is the largest proposed beneficiary – is not following its own rules for evaluating applications and maintaining records, the Government Accountability Office said this week.

Back | Next
Workers at Plant Vogtle assemble the steel bottom of the containment vessel for Unit 3. A report from the Government Accountability Office this week said a lack of accessible, consolidated data makes it difficult to manage the Department of Energy's federal loan guarantee program.  CHRIS THELEN/FILE
CHRIS THELEN/FILE
Workers at Plant Vogtle assemble the steel bottom of the containment vessel for Unit 3. A report from the Government Accountability Office this week said a lack of accessible, consolidated data makes it difficult to manage the Department of Energy's federal loan guarantee program.

Auditors said a lack of accessible, consolidated data makes it difficult to manage the program and provide competent oversight on applications for funding assistance designed to stimulate commercial energy projects, including construction of nuclear reactors.

Under a 2005 congressional edict, the department is authorized to award up to $34 billion in loan guarantees.

Georgia Power Co. and nuclear partners Oglethorpe Power and MEAG are conditionally approved to receive up to $8.326 billion for the Vogtle expansion.

That sum includes $3.460 billion for Georgia Power, $3.057 billion for Ogle­thorpe and $1.809 billion for MEAG.

Auditors reported difficulties getting documents needed for their review, noting that program officials “did not have consolidated data readily available and had to assemble these data over several months from various
sources.”

On a positive note, the GAO interviewed private lenders who finance large-scale energy projects, who concluded the Energy Department program’s review
process “was generally as stringent as or more stringent than their own.”

However, the government’s reviews sometimes differed from its established process in that some steps were skipped, not properly documented or omitted entirely. Such deficiencies make it difficult to treat all applicants consistently and could affect the ability to identify and mitigate project risks, the 58-page report said.

Poor documentation could also make it harder for the department to defend itself should the fairness or justifications for its loan guarantee decisions be called into question, auditors said.

The GAO recommended Energy Sec­re­tary Steven Chu establish a timetable for, and fully implement, a consolidated system to provide complete information on all loan guarantee projects, and that
the department regularly update the program’s policies and procedures.

The $14 billion project to add two reactors to Plant Vogtle was given final approval Feb. 9, when the Nuclear Regulatory Commission issued a combined operating license for the project.

The loan guarantee has not yet been finalized, as the financial terms of the agreement remain under negotiation, said Jeff Wilson, a Southern Co. spokesman.

He said the agreement is expected to become final in the second quarter of 2012. He would not elaborate on the specifics of those negotiations.

Comments (1) Add comment
ADVISORY: Users are solely responsible for opinions they post here and for following agreed-upon rules of civility. Posts and comments do not reflect the views of this site. Posts and comments are automatically checked for inappropriate language, but readers might find some comments offensive or inaccurate. If you believe a comment violates our rules, click the "Flag as offensive" link below the comment.
Little Lamb
50696
Points