Construction of MOX plant at SRS to continue through September

Construction of the mixed-oxide fuel fabrication facility will continue until at least through September without layoffs, according to the National Nuclear Security Administration.

 

On the same day the NNSA released a long-awaited analysis of alternative methods for plutonium disposition, the federal agency that manages the multibillion-dollar MOX program at Savannah River Site said construction could still be placed on standby when fiscal year 2015 begins Oct. 1.

“The NNSA intends to work with the contractor on a plan for placing the project in cold standby during (fiscal) 2015, and we are continuing our ongoing discussions with Congress as they review and evaluate the (fiscal) 2015 budget request,” according to a statement.

U.S. Sen. Lindsey Graham, South Carolina’s senior senator and a longtime supporter of the MOX program, applauded U.S. Energy Secretary Ernest Moniz for continuing construction through the end of the fiscal year, adding that he would fight for the future of the project.

“I thank the secretary for reversing course. This is the right decision for the program, the site and the employees working on the program at SRS,” Graham said. “In the short term, this decision will save thousands of jobs. However, there is still a long, arduous fight ahead.”

The MOX project is intended to convert 34 metric tons of U.S. weapons-grade plutonium into commercial reactor fuel and fulfill an international nonproliferation agreement with Russia. About $3.9 billion has been spent so far, and construction costs have reached an estimated $10 billion. In 1999, the MOX plant was projected to cost $1.7 billion.

The Department of Energy report released Tuesday analyzed the estimated life-cycle cost, schedule and ability to fulfill Russian agreements for five plutonium disposition methods, including the facility under construction at SRS.

The analysis determined that the contractor for the South Carolina MOX plant, Shaw Areva MOX Services, underestimated annual operating costs and issued change orders for several hundred million dollars. The life-cycle cost was an estimated $31 billion.

Options to the MOX plant include constructing a $50.5 billion fast-spectrum burner reactor and fuel fabrication facility at the K-Area Complex at SRS; immobilizing plutonium in glass canisters to dispose of in a geological repository for $28.7 billion; downblending plutonium for disposal in a salt-bed repository for $8.8 billion; and placing canisters of plutonium in 5,000-meter-deep shafts drilled into crystalline rock for an unknown cost.

The report also indicates that the four alternatives to the MOX plant at SRS would require further negotiations with Russia. Additionally, the SRS facility could complete disposition of 34 metric tons by 2043, the quickest of the options.

The NNSA said the report will be used “as a basis for determining the most efficient path forward for plutonium disposition.”

South Carolina Gov. Nikki Haley says state won't back down on MOX lawsuit
Savannah River Sites's MOX plant cost estimates challenged
Nuclear activists form new Savannah River Site watchdog group
Nunn and others buck Obama administration on MOX
MOX contractor tells employees construction work not changed
Nuclear Regulatory Commission reported no safety issues with MOX construction in 2013
South Carolina sues Energy Department over MOX shutdown
MOX standby renews community fears about jobs, site's future
Senators urge Energy Secretary Moniz to continue MOX construction
MOX facility at Savannah River Site placed on standby while alternatives assessed
Federal report calls for MOX cost analysis
TOPIC PAGE: Savannah River Site

More

Sun, 07/23/2017 - 00:05

Economic push sought in south Augusta

Sat, 07/22/2017 - 23:35

1,100 backpacks offered at event